Highway 549: Benton County > Travel Impacts

Construction Requires Lane Closures on Bella Vista Bypass in Bentonville

Crews will be using flagging operations, signage, and police enforcement to alternately close various lanes on roads connecting with the roundabout, including the northbound ramp to Highway 549, northbound and southbound North Walton Boulevard, and northbound I-49 during overnight hours.Apr 05 2020 to Apr 11 2020

Construction Requires Lane Closures on Bella Vista Bypass in Bentonville

Crews will be creating temporary traffic detours at the State Highway 549 (Bella Vista Bypass) roundaboutMar 26 2020 to Apr 05 2020

Rock Blasting Requires Lane Closures for Construction of the Bella Vista Bypass

During the blasting, crews will temporarily stop traffic for up to 15 minutes as a safety precaution.Mar 16 2020 to Mar 28 2020

Rock Blasting Requires Lanes Closures at Bella Vista Bypass in Bentonville

Construction to build a new Bella Vista Bypass interchange with U.S. Highway 71 in Bentonville requires rock blasting operations and intermittent lane closuresMar 02 2020 to Mar 11 2020

Construction Requires Lanes Closure on Bella Vista Bypass in Bentonville

Crews will be setting a concrete barrier wall along westbound State Highway 549 (Bella Vista Bypass) within the work zone east of the Punkin Hollow Road overpass to McKissic Creek RoadFeb 23 2020 to Mar 01 2020

Rock Blasting Requires Lanes Closures at Bella Vista Bypass in Bentonville

Crews will be performing rock blasting operations. During the blasting, crews will temporarily stop traffic for up to 15 minutes as a safety precaution.Feb 16 2020 to Feb 29 2020

Rock Blasting to Close Lanes at Bella Vista Bypass in Bentonville

During the blasting, traffic will temporarily be stopped for up to 15 minutes as a safety precaution in several locations.Dec 17 2019 to Jan 31 2020

Construction of U.S. Highway 71 Interchange for Bella Vista Bypass Requires Temporary Closures of State Highway 549

Construction of the U.S. Highway 71 Interchange for the Bella Vista Bypass will require temporary closures of State Highway 549Dec 09 2019 to Dec 13 2019

Rock Blasting to Close Lanes on Interstate 49 and State Highway 549 in Bentonville

During the rock blasting operations, traffic will temporarily be stopped for up to 15 minutes as a safety precaution in several locations.Nov 25 2019 to Dec 06 2019

Rock Blasting to Close Lanes on Interstate 49 and State Highway 549 in Bentonville

During the operations, traffic will temporarily be stopped for up to 15 minutes as a safety precaution in several locations.Nov 18 2019 to Nov 22 2019

Rock Blasting to Close Lanes on Interstate 49 and State Highway 549 in Bentonville

During the operations, traffic will temporarily be stopped for up to 15 minutes as a safety precaution in several locations.Nov 13 2019 to Nov 16 2019

Construction on Bella Vista Bypass Interchange in Bentonville Requires Overnight Lane Closures

Lanes on Interstate 49 and State Highway 549 (Bella Vista Bypass) will be closed during overnight hoursNov 04 2019 to Nov 09 2019

Improvements Require Lane Closures at Bella Vista Bypass Roundabout in Bentonville

Beginning Wednesday, April 26, crews will be placing final asphalt surface on the Bella Vista Bypass roundabout and approach ramps at the intersection with I-49, U.S. Highway 71 and U.S. Highway 71B (North Walton Boulevard).Apr 26 2017 to May 03 2017

Improvements Require Lane Shift at U.S. Highway 71B Exit in Bentonville

Beginning Friday, March 31, northbound traffic using the I-49 exit ramp (Exit 93) to southbound U.S. 71B will shift lanes to a newly constructed roundabout alignment.Mar 31 2017 to May 16 2017

Improvements Require Lane Shift at U.S. Highway 71B Exit in Bentonville

Beginning Monday morning, March 20, southbound traffic using the I-49 exit ramp (Exit 93) to U.S. 71B will shift lanes to a newly constructed ramp west of the existing alignment.Mar 20 2017 to Mar 23 2017

UPDATE! Improvements Require Lane Closures on U.S. Highway 71B in Bentonville

Motorists should expect traffic queuing for short periods of time as only one lane of traffic will remain open during the daily closures, which will be in effect weekdays from 7:30 a.m. to 6:00 p.m. Mar 09 2017 to Mar 24 2017

Improvements Require Lane Closures on U.S. Highway 71B in Bentonville

Beginning Monday, February 27, crews will be placing asphalt associated with the roundabout construction at I-49.Feb 27 2017 to Mar 10 2017

Improvements Require a Lane Closure on U.S. Business 71B in Benton County

Beginning Wednesday, February 8, the northbound outside lane of U.S. Highway 71B will be closed for roundabout construction at the interchange with Interstate 49.Feb 08 2017 to Apr 08 2017

Improvements Require a Lane Closure on Interstate 49 in Benton County

Beginning Monday, January 9, crews will be installing signs and the concrete barrier wall for widening the ramp and roundabout connection. The work will shift Exit 93 traffic to the inside shoulder of the ramp.Jan 09 2017 to Jul 20 2017

UPDATE! Improvements Require Lane Closure on Peach Orchard Road in Benton County

On Monday, August 22, crews will be installing cross drains on Peach Orchard Road.Aug 22 2016 to Aug 26 2016

CAP News What is the Connecting Arkansas Program?

Through a voter-approved constitutional amendment, the people of Arkansas passed a 10-year, half-cent sales tax to improve highway and infrastructure projects.

More
CAP Projects Which Projects Are Being Funded By This program?

Thirty-six projects in 19 corridors across Arkansas are included in the CAP, which improves transportation connections to the four corners of Arkansas.