Work on Interstate 30 Requires Lane Closures in Little Rock
Information Release
Arkansas Department of Transportation
NR 20-131
May 5, 2020
PULASKI COUNTY (05-05) – Crews performing design work along the Interstate 30 corridor in Little Rock will require frontage road, ramp and adjacent roadway lane closures, according to Arkansas Department of Transportation (ARDOT) officials.
Weather permitting, this work will occur during daytime hours Wednesday, May 6 through Friday, May 8, between 9:00 a.m. and 3:00 p.m.
- Westbound I-30 Exit Ramp to 2nd Street: Crews will close the right turn lane onto 2nd Street. Vehicles will still be able to turn right at the stop sign. The lane closure continues southbound on Ferry Street to 3rd Street.
- Westbound I-30 Frontage Road: Crews will close select lanes at Broadway Street.
- Adjacent City Streets: Crews will close select lanes and parking spots at the following intersections – Sherman and 2nd Streets, River Market and 4th Street, and Rock and 4th Streets. Crews will also close select lanes on eastbound/westbound Broadway Street west of the frontage road.
Traffic will be controlled with construction barrels and signage. Non-interstate traffic may also include flaggers. The public is advised to be cautious when traveling in the work zone.
The 30 Crossing project (Job CA0602) is part of ARDOT's Connecting Arkansas Program. More information on the CAP is available at ConnectingArkansasProgram.com.
Drivers should exercise caution when approaching and traveling through all highway work zones. Additional travel information can be found at IDriveArkansas.com or ARDOT.gov. You can also follow us on Twitter @myARDOT.