3 Press Release(s)
 
  1 Meeting Notification(s)
 

Overview

This project continues the widening of Interstate 630 eastward from the Big Rock Interchange. When complete, the additional lanes will increase capacity and improve traveler safety.

Project Updates

Job CA0608 Baptist Hospital – University Avenue
This project widens approximately 2.5 miles of Interstate 630 to eight lanes, extending generally from Baptist Hospital to University Avenue in Little Rock.

  • Construction Overview
    -Widening to 8 lanes between Baptist Hospital and University Avenue
    -Bridge and overpass construction at John Barrow Road, Rock Creek, Rodney Parham Road, Hughes Street, and University Avenue
    -Noise wall construction
    -Detours and nighttime lane closures
    -Estimated completion is Early 2020

Construction Newsletter


Updates:

  • Recent and Upcoming Construction
    - Hughes Street Bridge: Opened to traffic in October
    - Rock Creek Bridge: Erosion control and slope protection work
    - Baptist Health: Continued asphalt and excavation activities for temporary detours at I-630 eastbound on-ramp and westbound off-ramp
    - University Avenue: Temporary pavement at I-630 eastbound off-ramp (Exit 5), I-630 westbound off-ramp (Exit 5B), and I-630 westbound on-ramp

  • Lane Closures / Lane Shifts
    Beginning in late September, I-630 main lanes shifted toward the median to use the inside shoulder as a travel lane. Motorists need to be aware of the change in the traffic pattern. During this phase, traffic will also begin to utilize temporary detours that allow construction at on- and off-ramps.

    I-630 eastbound and westbound lanes will periodically be reduced to one open lane in each direction within the workzone during overnight hours and on Saturdays. See active lane closures in the table above. In general, mainlane closures can occur:
    - Sunday night, 6:00 p.m. to 6:00 a.m.
    - Monday through Thursday nights, 9:00 p.m. to 6:00 a.m.
    - Friday night at 9:00 p.m. to Saturday night at 11:59 p.m.

    During daytime travel peak hours, all six lanes on I-630 will be open to traffic. Nightly lane closures will occur throughout the life of the construction project

  • Hughes Street Overpass Opens
    After more than two months of construction, the new South Hughes Street Bridge over Interstate 630 in Little Rock opened to traffic three weeks ahead of schedule, according to Arkansas Department of Transportation (ARDOT) officials.

    The bridge opened Monday, October 1, reconnecting the Briarwood and University Park neighborhoods. Crews closed the bridge July 20 to demolish the structure and reconstruct it with a wider span as part of the I-630 construction job that is adding additional eastbound and westbound lanes between the Big Rock Interchange and University Avenue.

    Construction contractor Manhattan Road & Bridge estimated that it would take 96 days to replace the bridge, resulting in a late October completion. However, crews worked hard to reopen the bridge 23 days early, and Manhattan Road & Bridge will receive an early completion incentive of approximately $76,000.

  • Construction Cameras
    Traffic cameras have been installed along the project at select locations and can be viewed at IDriveArkansas.com.

  • Bid Opening
    ARDOT opened contractor bids in April 2018 and the Arkansas State Highway Commission approved a bid for improvements by Manhattan Road & Bridge Company and awarded the project for $87.4 million. Construction is estimated to take less than two years to complete.

  • Public Meeting
    A public involvement meeting was held February 3, 2015. The meeting presented and discussed the proposed plans to widen Interstate 630. A flier, comment form, and map can be downloaded here.
  • Noise Abatement Summary
    AHTD is moving forward with plans to construct noise walls along Interstate 630 in Noise Study Areas (NSA) 4, 5, and 6. These proposed noise walls are on the north side of I-630, approximately located between North Rodney Parham Road and South McKinley Street. This is based on community support and because of the advantages noise walls have over noise soil berms, including greater noise reduction benefits, less maintenance, and fewer impacts to public use of the right of way. The approved noise walls are proposed to be installed during the widening project, which is estimated to start construction in mid 2017.

    Figure 3: NSA 4 & 5 - Wall 2 & Wall 3Figure 3: NSA 4 & 5 - Wall 2 & Wall 3
    Figure 7: NSA 6 - Wall 4Figure 7: NSA 6 - Wall 4

    A proposed noise wall in NSA 8 on the south side ofI-630 in University Park will not be constructed. More than 50% of benefited residences opposed a noise wall being constructed along Arthur Drive. Download Noise Abatement Summary
  • I-630 Noise Study Report
    The I-630 Noise Study Report has been updated since the draft was released in fall 2015. Additional analyses have been conducted to determine the potential for noise barriers in eight Noise Study Areas (NSA) along the I-630 corridor between Baptist Hospital and University Avenue. I-630 Noise Study Report (Updated)

Preliminary Schedule:

View CA0608 Project Map

Schedules are preliminary and are subject to change as project development progresses.

 

CAP News What is the Connecting Arkansas Program?

Through a voter-approved constitutional amendment, the people of Arkansas passed a 10-year, half-cent sales tax to improve highway and infrastructure projects.

More
CAP Projects Which Projects Are Being Funded By This program?

Thirty-six projects in 19 corridors across Arkansas are included in the CAP, which improves transportation connections to the four corners of Arkansas.

More
CAP Frequently Asked Questons Visit the FAQ Section For More Answers!

A collection of some of the most frequently asked questions concerning the Connecting Arkansas Program and the projects funded by the 10-year, half-cent sales tax.

More