1 Travel Impacts(s)
 
 3 Press Release(s)
 
  3 Meeting Notification(s)
 

This project proposes to enhance one of the most traveled roads in Arkansas. When complete, the improvements will enhance the transportation connection through central Arkansas, increase capacity, and improve traveler safety.

Project Updates

The Arkansas Department of Transportation issued design-builder Kiewit-Massman Construction a Notice to Proceed (NTP) in January 2020. As part of NTP #1, Kiewit-Massman is beginning design-focused tasks for roadway and bridge elements, including design of the new Arkansas River Bridge, developing maintenance of traffic plans, performing geotechnical drilling and testing, and preparing master agreements for utility relocation. Any actual construction-related activities will begin upon issuance of a future second Notice to Proceed by ARDOT.

Environmental Documents


Travel ImpactsFromTo
Geotechnical boring for design work on the 30 Crossing project will require eastbound and westbound lane closures in select areas on Interstate 30 and adjacent ramps and city streets
Read More
Feb 24, 2020Mar 04, 2020


Project Scope

Phase 1 of the 30 Crossing Project will include areas of construction in Little Rock and North Little Rock. Remaining portions of the 30 Crossing project will be constructed in future phases.

Arkansas River Bridge

  • The Arkansas River Bridge will be reconstructed to three through lanes with two collector-distributor lanes and an auxiliary lane in both directions.

  • The bridge will include an improved opening for the Arkansas River navigational channel.

North Little Rock

  • In North Little Rock, additional lanes continue eastbound through the Broadway Street interchange to Bishop Lindsey Avenue. The Broadway Street interchange will also be reconstructed.

  • Beginning at Bishop Lindsey Avenue, the project includes new pavement and re-striping eastbound I-30 to four lanes to the interchange with I-40 (North Terminal). This creates a fourth lane without widening the freeway or bridge structures to add capacity.

  • The Curtis Sykes Drive entrance ramp to eastbound I-30 will be north and east to tie into I-40 east.

  • Portions of the North Terminal will be reconstructed to remove an eastbound I-40 weaving issue between the North Terminal and the I-40/Highway 67 interchange. A bridge will be constructed to carry eastbound I-30 entrance ramp traffic over I-40 eastbound ramp lanes to enter traffic in the far-left eastbound lanes.

Little Rock

  • In Little Rock, I-30 improvements continue above a reconstructed I-30/Hwy. 10 (Cantrell Road) interchange (split diamond) and continues with four main lanesin both directions between 3rd Street and 9th Street.

  • A new wider bridge over I-30 will be constructed at 6th Street.

  • The Hwy. 10 interchange will be reconstructed as a split-diamond interchange. This will remove the clover leaf ramps and provide direct ramp access with the frontage roads.

    • Highway 10 will be reconstructed along existing 2nd Street and extended from Cumberland Drive, below I-30, to Maholon Martin Street.
    • The clover leaf ramps will be removed and the right-of-way between President Clinton Avenue and 3rd Street will be regraded to accommodate future use as a public space.
    • Mahlon Martin Street will be extended and improved from East 4th Street to President Clinton Avenue.
  • There are several ramp improvements at the I-630 interchange.

    • Two eastbound I-630 ramp lanes will enter I-30 eastbound rather than being reduced to one lane.
    • A new ramp lane will be constructed from the eastbound I-630 ramp to the eastbound I-30 frontage road.
    • A second lane will be added from the westbound frontage road entrance ramp to I-30 westbound at I-630.
    • East and West I-30 main lanes through the I-630 interchange narrowed from three to two lanes in both directions.

Download Construction Phase 1 Map


Preliminary Schedule (subject to change)

  • January 2020 - NTP #1 issued to Kiewit-Massman Construction to begin work on project design-related tasks

  • Mid 2020 - Utility relocations estimated to start

  • Late 2020/Early 2021 - Construction estimated to start

  • Mid 2021 - Design estimated to complete


Schedules are preliminary and are subject to change as project development progresses.

 

Travel Impacts

Geotechnical Work on Interstate 30 Requires Lane Closures in Little Rock and North Little Rock

From Feb 24, 2020 to Mar 04, 2020

Visit IDriveArkansas.com for up to date traffic information and travel conditions.

CAP News What is the Connecting Arkansas Program?

Through a voter-approved constitutional amendment, the people of Arkansas passed a 10-year, half-cent sales tax to improve highway and infrastructure projects.

More
CAP Projects Which Projects Are Being Funded By This program?

Thirty-six projects in 19 corridors across Arkansas are included in the CAP, which improves transportation connections to the four corners of Arkansas.

More
CAP Frequently Asked Questons Visit the FAQ Section For More Answers!

A collection of some of the most frequently asked questions concerning the Connecting Arkansas Program and the projects funded by the 10-year, half-cent sales tax.

More